SECOND DIVISION
G.R. No. 218663. February 28, 2022
MUNICIPALITY OF CORELLA, REPRESENTED BY MAYOR JOSE NICANOR D. TOCMO, Petitioner, v. PHILKONSTRAK DEVELOPMENT CORPORATION AND VITO RAPAL, Respondents.
D E C I S I O N
HERNANDO, J.:
This petition for review on certiorari1 under Rule 45 of the Rules of Court assails the January 30, 2015 Decision2 and June 9, 2015 Resolution3 of the Court of Appeals (CA) in CA-G.R. SP. No. 06516, affirming in toto the October 27, 2011 Decision4 and November 25, 2011 Order5 of the Construction Industry Arbitration Commission (CIAC) in CIAC Case No. 19-2011 entitled "Philkonstrak Development Corp. v. Municipality of Corella, represented by Hon. Jose Nicanor D. Tocmo and Hon. Vito B. Rapal, in his personal capacity." The Municipality of Corella, represented by Mayor Jose Nicanor D. Tocmo (Tocmo), was ordered to pay Philkonstrak6 Development Corporation (Philkonstrak) the amount of P12,844,650.00.
The Antecedents:
Corella is a municipality located in Bohol. It is represented by its municipal mayor, Tocmo.7 On the other hand, Philkonstrak is a corporation duly organized and existing under Philippine laws. It is a private firm engaged in the business of design/build construction.8 Vito Rapal (Rapal) was the former mayor of Corella.9 During the pendency of the proceedings, Rapal is the Vice-Mayor of Corella.10chanRoblesvirtualLawlibrary
Sometime in 2009, Corella conducted a public bidding for the rehabilitation and improvement of its municipal waterworks system project. Philkonstrak emerged as the winning bidder.11chanRoblesvirtualLawlibrary
Subsequently, Corella, through then Mayor Rapal, entered into a contract agreement12 (contract) with Philkonstrak for the rehabilitation and improvement of the municipal waterworks system for a total amount of P15,997,732.63.13chanRoblesvirtualLawlibrary
Pursuant to the contract, Philkonstrak procured the materials, equipment, and the labor force for the mobilization of the construction works. During the course of the project, Philkonstrak submitted progress reports to the municipal engineer of Corella for coordination and supervision.14chanRoblesvirtualLawlibrary
As of December 2009, Philkonstrak accomplished more than 50% of the work essential for the project for which Philkonstrak expended the amount of P8,233,000.00.15 When Corella, through Tocmo, refused to pay and denied liability, Philkonstrak was forced to suspend its construction works.16 Consequently, Philkonstrak sent Corella, through Tocmo, a formal demand letter17 to pay for the actual expenses incurred by Philkonstrak. Philkonstrak also sent a demand letter18 to Rapal.
Tocmo, in his reply,19 denied liability and questioned the validity of the contract. He averred that Rapal had no authority to enter into such contract during his term as mayor of Corella.20chanRoblesvirtualLawlibrary
On April 28, 2011, Philkonstrak filed before the CIAC a complaint21 for collection of sum of money against Corella and Rapal, as Rapal was the mayor at the time the contract was signed and whose signature appeared thereon. The case was docketed as CIAC Case No. 19-2011.
In its complaint, Philkonstrak claimed, among others, that it had already undertaken more than 50% of the construction work for the completion of the project, which caused it to incur the amount of Php 8,233,000.00, excluding other materials that were not yet installed as per the completion report.22chanRoblesvirtualLawlibrary
According to Philkonstrak, Tocmo refused to pay the obligation on behalf of Corella primarily because of his political differences with Rapal.23 Philkonstrak averred that it had no knowledge of the underlying issues between the administrations of Tocmo and Rapal, and that it merely complied faithfully with the terms of the contract.24chanRoblesvirtualLawlibrary
Philkonstrak prayed for attorney's fees, legal interest, exemplary damages, arbitration fees, and other expenses.25chanRoblesvirtualLawlibrary
On August 1, 2011, Rapal filed his answer,26 admitting the material allegations of the complaint and averring that he was authorized to enter into the contract with Philkonstrak for the rehabilitation/improvement of the waterworks system of Corella27 in accordance with Municipal Ordinance No. 2010-0228 or "An Ordinance Appropriating the Amount of Twenty-Seven Million Pesos (Php 27,000,000.00) for the Purchase of the Following Heavy Equipment: One Unit Brand New Road Grader, One Unit Reconditioned Road Roller, and Rehabilitation/Improvement on the Existing Waterworks System of the [Local Government Unit]."29chanRoblesvirtualLawlibrary
On August 19, 2011, Corella filed its answer,30 denying the material allegations of the complaint. It asserted that the contract is not binding because Municipal Ordinance No. 2010-02 was in violation of Article 107(g) of the Implementing Rules and Regulations (IRR) of Republic Act No. (RA) 716031 otherwise known as the "Local Government Code of 1991."
Furthermore, Corella contended that Rapal was in bad faith since he knew that the municipal ordinance was defective and ineffective; thus, he was not legally authorized to enter into a contract with Philkonstrak for lack of a valid municipal ordinance.32
Ruling of the Construction Industry Arbitration Commission: |
WHEREFORE, the Tribunal hereby decides and awards in full and final disposition of this arbitration, as follows:Aggrieved, Corella filed a motion for correction of final award35 dated November 21, 2011, claiming that the award of P4,000,000.00 for the uninstalled materials should be deleted because it is inconsistent and contradictory to the quantum meruit principle applied by the CIAC.
(a) Respondent Municipality of Corella, Bohol is hereby ordered to pay [Philkonstrak] its (i) claim in the amount of Php 8,233,000.00, representing the value of work done and material supplied for the rehabilitation and improvement of the waterworks system of respondent Municipality and (ii) the claim in the amount of Php 4,000,000.00 representing the value of materials needed for the rehabilitation and improvement of the waterworks system of Respondent Municipality which [Philkonstrak] had purchased and delivered but were not installed due to the repudiation of the Contract by Respondent Municipality of Corella.
(b) Respondent Municipality of Corella is hereby ordered to pay [Philkonstrak] the amount of Php 611,650.00 representing accrued legal interest; provided that if the principal amounts decreed in paragraph (a) above are not fully paid after the award shall have become final and executory, the said principal amounts shall earn interest at the legal rate of 12% per annum computed from the date this award shall become final and executory and until whole amount is fully paid.
(c) [Philkonstrak's] claims for attorney fees and exemplary damages are denied.
(d) [Philkonstrak] shall pay two-third (2/3) and Respondent Municipality of Corella shall pay one-third (1/3) of the cost of arbitration which shall include the following:
chanroblesvirtuallawlibrary(e) All other requests for relief not granted or disposed of here are hereby denied.
Total Arbitration Fee [Philkonstrak's] Share (75%) [Municipality of Corella's] Share (25%)(i) Filing Fee P22,346.79 P16,782.59 P5,564.20(ii) Administrative Fee 23,666.79 17,750.09 5,916.70(iii) Arbitrators' Fees 287,118.82 215,339.12 71,779.70(iv) Arbitration Dev't Fund 17,844.65 13,383.49 4,461.16 P350,977.05 P263,255.29 P87,721.76
Summary of AwardFurther, [Municipality of Corella] shall reimburse the amount advanced by [Philkonstrak] in the amount of eighty-seven thousand seven hundred twenty-one pesos and 76/100 (P87,721.76) representing one third of the total arbitration fees.34chanRoblesvirtualLawlibrary
Nature of Claim Amount Claimed Amount Awarded [Philkonstrak's] claim for unpaid billings for work done and material supplied P8,233,000.00 P8,233,000.00 [Philkonstrak's] claim for material purchased and delivered but not installed P4,000,000.00 P4,000,000.00 [Philkonstrak's] claim for accrued interest P611,650.00 P611,650.00 [Philkonstrak's] claim for attorney's fees P2,500,000.00 none [Philkonstrak's] claim for exemplary damages P2,500,000.00 noneTotal P17,844,650.00 P12,844,650.00
WHEREFORE, the Petition is DISMISSED. The CIAC's Decision dated October 27, 2011 and its Order dated November 25, 2011 are AFFIRMED in toto.The CA denied Corella's motion for reconsideration in its Resolution46 dated June 9, 2015, finding no new, valid, and justifiable ground or reason that would compel it to alter or reverse its ruling.
SO ORDERED.45chanRoblesvirtualLawlibrary
1. Can a mayor enter into a contract with a corporation without prior authorization from the sangguniang bayan as required by [RA] 7160 and [RA] 9184?Summarizing all four questions, the main issue in the case at bar is this: whether or not the CA is correct in affirming the Decision of the CIAC which found that the contract between Philkonstrak and Corella was valid, and which ordered Corella to pay Philkonstrak the amount of P12,844,650.00 for breach of the same.
2. Can a mayor enter into a contract with a corporation without the proper appropriation of public funds as required by the 1987 Constitution as reflected in Presidential Decree 1445 and Executive Order 292?
3. Will a [Department of Interior and Local Government] Circular prevail over the EN BANC Decision of the Supreme Court in Quisumbing, et al. v. Garcia, et al. docketed as G.R. No. 175527 dated December 8, 2008?
4. Can a final and executory decision of a quasi-judicial agency (CIAC) still be subject to judicial review?48chanRoblesvirtualLawlibrary
No separate sangguniang bayan authorization is necessary when the appropriation ordinance is sufficient in detail. |
SECTION 22. Corporate Powers.Second, RA 918450 or the "Government Procurement Reform Act," specifically the last paragraph of Section 37, to wit:
x x x x
(c) Unless otherwise provided in this Code, no contract may be entered into by the local chief executive in behalf of the local government unit without prior authorization by the sanggunian concerned. A legible copy of such contract shall be posted at a conspicuous place in the provincial capitol or the city, municipal or barangay hall.
x x x x
ARTICLE 107. Ordinances and Resolutions. - The following rules shall govern the enactment of ordinances and resolutions:
x x x x
(g) No ordinance or resolution passed by the sanggunian in a regular or special session duly called for the purpose shall be valid unless approved by a majority of the members present, there being a quorum. Any ordinance or resolution authorizing or directing the payment of money or creating liability, shall require the affirmative vote of a majority of all the sanggunian members for its passage. (Emphasis supplied)
SECTION 37. Notice and Execution of Award. - x x xTocmo asserts that before then Mayor Rapal entered into the contract on behalf of Corella with Philkonstrak, two requirements were necessary to be met:51 (1) prior authorization from the sangguniang bayan of Corella, in accordance with Section 22(c) of the Local Government Code and Section 37 of the Government Procurement Act; and (2) the appropriation ordinance or resolution authorizing or directing the payment of money or creating a liability,52 in accordance with Article 107(g) of the IRR of the Local Government Code.
x x x x
The Procuring Entity shall issue the Notice to Proceed to the winning bidder not later than seven (7) calendar days from the date of the approval of the contract by the appropriate authority. All notices called for by the terms of the contract shall be effective only at the time of receipt thereof by the contractor. (Emphasis supplied)
18. The contract merely describes the contracting parties as the "Municipality of Corella" and "Philkonstrak Development Corporation" and signed by Respondent Vito B. Rapal and Jesse J. Ang. Nowhere is there any showing that the contract contains the "prior authorization of the sanggunian concerned." No ordinance authorizing respondent Rapal to enter into a contract was made an integral part of the contract. The contract besides being 149 pages long does not contain any prior authorization ordinance. Page two of the contract, which outlines the contract documents, does not include an ordinance authorizing respondent Rapal to enter into a contract with Philkonstrak.54 (Emphasis supplied)The Court disagrees. It must be emphasized that such issue is not novel.
Explained simply, the [Local Government Code] requires the local chief executive to secure prior authorization from the sanggunian before he can enter into contracts on behalf of the LGU. A separate prior authorization is no longer required if the specific projects are covered by appropriations of the LGU. The appropriation ordinance passed by the sanggunian is the local chief executive's authority to enter into a contract implementing the project.As the Verceles case explained, "sufficient authority" in an appropriation ordinance simply means specifically and expressly setting aside an amount of money for a certain project or program.58chanRoblesvirtualLawlibrary
As required in Quisumbing, the local chief executive must inquire if the provisions in the appropriation ordinance specifically covers the expense to be incurred or the contract to be entered into.
If the project or program is identified in the appropriation ordinance in sufficient detail, then there is no more need to obtain a separate or additional authority from the sanggunian. In such case, the project and the cost are already identified and approved by the sanggunian through the appropriation ordinance. To require the local chief executive to secure another authorization for a project that has been specifically identified and approved by the sanggunian is antithetical to a responsive local government envisioned in the Constitution and in the [Local Government Code].57 (Emphasis supplied)
An appropriation ordinance requires the affirmative vote of a majority of all the sanggunian members. |
Hence, for all intents and purposes, the legislative process has been completed, and that the subject ordinance [Municipal Ordinance No. 2010-02] is now accorded with the presumption of validity. Moreover, it might interest you to know that DILG Central Office had the occasion to opine, under DILG Opinion No. 103 S 2001 dated December 18, 2001, that the Local Government Code of 1991 does not expressly prescribe for a specific voting requirement for the passage of an appropriation ordinance. Hence, the general rule on the passage of an ordinance should be made to apply. The pertinent provision on the matter is Article 107 (g) of the Rules and Regulations Implementing R.A. 7160 x x x.61 (Emphasis supplied)Both the CIAC and the CA applied the opinion of the Regional Director of the DILG to their Decisions, noting that Tocmo, the present Mayor, did not take any steps to question the validity of the Opinion, thus, it had become final and binding on the concerned parties.
The CIAC Decision is not anymore subject to judicial review. |
Since the motion for correction did not fall under any of the grounds provided by the CIAC's Rules, it is considered a motion for reconsideration and a prohibited pleading. It did not interrupt the running of the fifteen (15) days period for petitioner to file its petition to this Court. Consequently, after the lapse of the fifteen (15) days from November 10, 2011 or on November 25, 2011, the CIAC's decision has already become final and executory because petitioner failed to file its petition for review within the period provided by law. The CIAC was correct to issue on January 19, 2012 an Order, declaring that the Final Award has become final and executory.The Court agrees. As aptly pointed out by Senior Associate Justice Estela M. Perlas-Bernabe during the deliberations of this case, a CIAC Final Award, equivalent to a trial court final decision as opposed to a partial award or decision, is still susceptible to judicial review. However, when availing of judicial reliefs against a CIAC Final Award, one must still abide by the procedural framework set therefor, such as the periods of appeal and prohibited motions. If the said party fails to comply, he or she is equally bound by the finality of judgment principle.
Settled is the rule that a judgment that has become final and executory is immutable and unalterable. The judgment may no longer be modified in any respect, even if the modification is meant to correct what is perceived to be an erroneous conclusion of fact or law, and regardless of whether the modification is attempted to be made by the court rendering it or by the highest court of the land. While there are recognized exceptions - e.g., the correction of clerical errors, the so-called nunc pro tunc entries which cause no prejudice to any party, void judgments, and whenever circumstances transpire after the finality of the decision rendering its execution unjust and inequitable - none of these exceptions apply to the present case.66 (Emphasis supplied)
A definitive final judgment, however erroneous, is no longer subject to change or revision.The CA nor this Court may not anymore step in to modify or correct a quasi-judicial agency's decision that has already been deemed final and executory. If this were so, then there would be no end to litigation stemming from the CIAC, which is against the expeditious nature of such proceedings and hence, against the public policy underlying arbitration.
A decision that has acquired finality becomes immutable and unalterable. This quality of immutability precludes the modification of a final judgment, even if the modification is meant to correct erroneous conclusions of fact and law. And this postulate holds true whether the modification is made by the court that rendered it or by the highest court in the land. The orderly administration of justice requires that, at the risk of occasional errors, the judgments/resolutions of a court must reach a point of finality set by the law. The noble purpose is to write finis to dispute once and for all. This is a fundamental principle in our justice system, without which there would be no end to litigations. Utmost respect and adherence to this principle must always be maintained by those who exercise the power of adjudication. Any act, which violates such principle, must immediately be struck down. Indeed, the principle of conclusiveness of prior adjudication is not confined in its operation to the judgments of what are ordinarily known as courts, but extends to all bodies upon which judicial powers had been conferred.69chanRoblesvirtualLawlibrary
Since Corella's Motion was not based on any of the enumerated grounds under Section 17.2, the fifteen-(15) day period to file a petition for review before the CA was not suspended. As Corella received the CIAC Decision on November 10, 2011,73 it had until November 25, 2011 to file its petition for review. Thus, when Corella filed its Rule 43 petition before the CA on December 26, 2011, the same was already filed out of time and hence, executory and immutable.RULE 17
Post-Award Proceedings
SECTION 17.1 Motion for Correction of Final Award - Any of the parties may file a motion for correction of the Final Award within fifteen (15) days from receipt thereof upon any of the following grounds:
- an evident miscalculation of figures, a typographical or arithmetical error;
- an evident mistake in the description of any party, person, date, amount, thing or property referred to in the award;
- where the arbitrators have awarded upon a matter not submitted to them, not affecting the merits of the decision upon the matter submitted;
- where the arbitrators have failed or omitted to resolve certain issue/s formulated by the parties in the Terms of Reference (TOR) and submitted to them for resolution; and
- where the award is imperfect in a matter of form not affecting the merits of the controversy.
x x x x17.1.2 A motion for correction upon grounds other than those mentioned in this section shall not interrupt the running of the period for appeal.x x x xRULE 18Execution of Final Award
SECTION 18.1 Execution of Award. - A final arbitral award shall become executory upon the lapse of fifteen (15) days from receipt thereof by the parties.
SECTION 18.2 Petition for Review. - A petition for review from a final award may be taken by any of the parties within fifteen (15) days from receipt thereof in accordance with the provisions of Rule 43 of the Rules of Court.
x x x x
SECTION 18.5 Execution/Enforcement of Awards. - As soon as a decision, order or final award has become executory, the Arbitral Tribunal (or the surviving remaining member/s), shall, motu proprio or on motion of the prevailing party issue a writ of execution requiring any sheriff or proper officer to execute said decision, order or final award. If there are no remaining/surviving appointed arbitrator/s, the Commission shall issue the writ prayed for.
x x x x
The principle of quantum meruit is applicable in this case. |
(b) The Municipality of Corella is hereby ordered to pay Philkonstrak accrued legal interest from the time the CIAC Decision became final on October 27, 2011, at the rate of 12% per annum, until June 30, 2013. From July 1, 2013 until full payment of the amount is made, the accrued legal interest shall be 6% per annum.81 The total of the foregoing amount shall earn interest at the rate of six percent (6%) per annum from finality of the Decision until full payment.
(i) The amount of P8,233,000.00, representing the value of work done and materials supplied for the rehabilitation and improvement of the waterworks system of the Municipality of Corella; (ii) The amount of P4,000,000.00 representing the value of materials needed for the rehabilitation and improvement of the waterworks system of the Municipality of Corella which Philkonstrak Development Corporation had purchased and delivered but were not installed due to the repudiation of the Contract Agreement by the Municipality of Corella.
[The] cost of arbitration which includes the filing, administrative, arbitrators' fees and charges for Arbitration Development Fund, including all incidental expenses, shall be on pro rata basis (or other modes of sharing), subject to the determination of the Arbitral Tribunal which of the parties shall eventually shoulder such cost or the mode of sharing thereof.83chanRoblesvirtualLawlibraryThe mode of sharing as determined by the Construction Industry Arbitration Commission is affirmed by this Court, which is as follows:
Thus, the Municipality of Corella shall reimburse the amount advanced by Philkonstrak Development Corporation in the amount of P87,721.76, representing one-third of the total arbitration fees.
Total Arbitration Fee Philkonstrak's Share (75%) Municipality of Corella's Share (25%)(i) Filing Fee P22,346.79 P16,782.59 P5,564.20(ii) Administrative Fee 23,666.79 17,750.09 5,916.70(iii) Arbitrators' Fees 287,118.82 215,339.12 71,779.70(iv) Arbitration Dev't Fund 17,844.65 13,383.49 4,461.16 P350,977.05 P263,255.29 P87,721.76
Endnotes:
1 Rollo, pp. 3-60.
2 Id. at 85-96. Penned by Associate Justice Renato C. Francisco and concurred in by Associate Justices Gabriel T. Ingles and Pamela Ann Abella Maxino.
3 Id. at 101-102.
4 Id. at 62-84. Penned by Chairman Eduardo R. Ceniza and concurred in by Members Tomasito Z. Academia and Guadalupe O. Mansueto.
5 Id. at 295-297.
6 Spelled Philconstrak or Philkonstruct in some parts of the records.
7 Rollo, p. 85.
8 Id.
9 Id. at 86.
10 Id.
11 Id.
12 CA rollo, pp. 113-115.
13 Id. at 113.
14 Rollo, p. 86.
15 Id.
16 Id.
17 CA rollo, pp. 101-102.
18 Id. at 103-104.
19 Id. at 105.
20 Rollo, p. 86.
21 CA rollo, pp. 13-19.
22 Id. at 13-16.
23 Id. at 15.
24 Id. at 16.
25 Id. at 17.
26 Id. at 292-303.
27 Rollo, p. 87.
28 CA rollo, p. 263.
29 Id.
30 Id. at 260-262.
31 Entitled "AN ACT PROVIDING FOR A LOCAL GOVERNMENT CODE OF 1991." Approved on October 10, 1991.
32 Rollo, p. 88.
33 Id. at 62-84.
34 Id. at 83-84.
35 CA rollo, pp. 345-346.
36 Id. at 295-297.
37 Id.
38 Rollo, pp. 300-302.
39 CA rollo, pp. 347-350.
40 Id. at 349.
41 Id. at 3-11.
42 Id.
43 Id.
44 Rollo, pp. 85-96.
45 Id. at 95.
46 Id. at 101-102.
47 Id. at 3-60.
48 Id. at 3.
49 Id. at 14.
50 Entitled "AN ACT PROVIDING FOR THE MODERNIZATION, STANDARDIZATION AND REGULATION OF THE PROCUREMENT ACTIVITIES OF THE GOVERNMENT AND FOR OTHER PURPOSES." Approved on January 10, 2003.
51 Rollo, pp. 15-18.
52 Id. at 18-25.
53 Id. at 15-16.
54 Id.
55 593 Phil. 655-677 (2008).
56 794 Phil. 629-661 (2016).
57 Id. at 645-646.
58 See id.
59 CA rollo, pp. 595-599.
60 Id. at 465-466.
61 Rollo, pp. 68-69 and 94-95.
62 Philippine Duplicators, Inc. v. National Labor Relations Commission and Philippine Duplicators Employees Union-Tupas, 298 Phil. 552, 562 (1993).
63 See Adasa v. Abalos, 545 Phil. 168 (2007).
64 Rollo, pp. 68-69.
65 Section 17.2 reads:
chanroblesvirtuallawlibrarySECTION 17.2. Motion for Reconsideration or New Trial. - A motion for reconsideration or new trial shall be considered a prohibited pleading.66 Rollo, p. 93.
67 G.R. No. 233781, July 8, 2019.
68 582 Phil. 357, 366-367 (2008).
69 Department of Labor and Employment v. Kentex Manufacturing Corporation, supra.
70 Sec. 18.2.
71 Sec. 17.1.2.
72 Sec. 18.1.
73 Rollo, p. 93.
74 Aguinaldo IV v. People, G.R. No. 226615, January 13, 2021, citing Uy v. Del Castillo, 814 Phil. 61, 74-75 (2017).
75 See Taisei Shimuzu Joint Venture v. Commission on Audit, G.R. No. 238671, June 2, 2020, citing Argel v. Singson, 757 Phil. 228, 236-237 (2015).
76 Geronimo v. Commission on Audit, G.R. No. 224163, December 4, 2018.
77 Id.
78 Id.
79 Rollo, p. 39.
80 Id.
81 Nacar v. Gallery Frames, 716 Phil. 267, 282-283 (2013).
82 Rollo, p. 82.
83 Id.cralawredlibrary