EN BANC
G.R. No. 252411. February 15, 2022
METRO LAUNDRY SERVICES, REPRESENTED BY ROWELA T. TINDOG, HEIR OF PROPRIETOR, MS. ELIZABETH T. TINDOG, Petitioner, v. THE COMMISSION PROPER, COMMISSION ON AUDIT, AND THE CITY OF MANILA, Respondents.
R E S O L U T I O N
LOPEZ, M., J.:
This Petition for Certiorari1 under Rule 64, in relation to Rule 65, of the Revised Rules of Court assails the Commission on Audit (COA) Proper Decision No. 2020-0432 dated January 10, 2020, which denied Metro Laundry Services' (Metro Laundry) money claim for the unpaid services it rendered at the Ospital ng Maynila Medical Center (OMMC).
WHEREFORE, premises considered, the Petition for Money Claim of [Metro Laundry], represented by its Proprietor, Ms. Elizabeth T. Tindog, against the City Government of Manila, for payment of laundry services rendered to the [OMMC] from April to December 2011, amounting to [P]1,851,814.45, is hereby DENIED.41 (Emphases in the original.)COA Chairperson Michael G. Aguinaldo (Chairperson Aguinaldo) dissented42 in the outright denial of Metro Laundry's money claim. Without discounting the admitted illegality of the transaction, Chairperson Aguinaldo cited case laws which upheld payment of compensation to a contractor or service provider by way of quantum meruit despite defects in or even nullity of the contract. In his Dissenting Opinion,43 he opined:
[T]he Decision makes much reliance on COA Resolution No. [86-58] dated [November 15, 1986,] which states the policy on the Recovery by Government Contractors on the Basis of Quantum Meruit. This Resolution, which curiously limits quantum meruit recovery to a single ground - the absence of the certificate of availability of funds, has long been rendered obsolete by numerous decisions of the Supreme Court through the last three decades. It is archaic, a relic of the past, and totally out of tune with[,] not just jurisprudence[,] but reality. Relying on the Resolution as a basis for the denial of the money claim is not simply turning a blind eye to jurisprudence[,] but being inattentive and unjust.Metro Laundry now comes directly to the Court on certiorari, insisting to be paid on the basis of quantum meruit for the services it had actually rendered for the City of Manila.45 For its part, the COA Proper, through the Office of the Solicitor General (OSG), points out Metro Laundry's failure to file a motion for reconsideration (MR) before the COA Proper before it sought remedy to the Court, which would have warranted the dismissal of the petition.46 Nevertheless, the OSG prays for the modification of the assailed Decision No. 2020-043 as it also argues for Metro Laundry's entitlement to compensation and the application of the principle of quantum meruit since the City of Manila had admittedly benefited from Metro Laundry's services, subsequent appropriations for the payment were already done, and disbursement vouchers were correspondingly issued therefor.47 However, the OSG takes exception to the grant of the whole amount of P1,851,814.45 claimed, and instead argues that only the amount appearing in the disbursement vouchers - a total of P1,666,633.00 - should be granted.48chanRoblesvirtualLawlibrary
The justification usually given for the denial of money claims based on quantum meruit is that contractors continue to violate government procurement laws. But who actually violates the procurement law? Absent any proof of collusion, the burden of which falls on the Commission, it cannot be presumed that the contractor colluded with the government officials involved. It is the government official who violates the procurement law, by not holding any public bidding, or proceeding without appropriation or a written contract. Consequently, the proper party to penalize is the government official responsible. The denial of a quantum meruit money claim, in the absence of proof of collusion, will not have the effect of lessening procurement law violations for the simple reason that the wrong person is being penalized. The proper recourse is referral of the matter to the Office of the Ombudsman for investigation of the government officials involved.
x x x x
I vote to grant the Petition for Money Claim, subject to a quantum meruit determination of the actual services rendered and the reasonable value thereof.44chanRoblesvirtualLawlibrary
Non-filing of MR does not justify dismissal of the petition. |
Payment for services done on account of the government cannot be avoided despite irregularity or nullity of the contract. |
SEC. 85. Appropriation Before Entering Into Contract. —We, however, highlight that the OMMC and the City of Manila have consistently recognized Metro Laundry's entitlement to payment for its actual services rendered despite non-compliance with the foregoing provisions as shown by the series of certifications, indorsements, and vouchers issued by OMMC and concerned city officials.55 Even the COA Proper, in its assailed Decision No. 2020-043,56 agreed that Metro Laundry is entitled to be paid for its services, although it took exception to Metro Laundry's recourse against the local government due to the invalidity of the contract, and for that sole reason, denied Metro Laundry's claim outright.57chanRoblesvirtualLawlibraryx x x x
- No contract involving the expenditure of public funds shall be entered into unless there is an appropriation therefor, the unexpended balance of which, free of other obligations, is sufficient to cover the proposed expenditure.
SEC. 86. Certificate Showing Appropriation to Meet Contract. — Except in the case of a contract for personal service, for supplies for current consumption or to be carried in stock not exceeding the estimated consumption for three months, or banking transactions of government-owned or controlled banks[,] no contract involving the expenditure of public funds by any government agency shall be entered into or authorized unless the proper accounting official of the agency concerned shall have certified to the officer entering into the obligation that funds have been duly appropriated for the purpose and that the amount necessary to cover the proposed contract for the current fiscal year is available for expenditure on account thereof, subject to verification by the auditor concerned. The certificate signed by the proper accounting official and the auditor who verified it, shall be attached to and become an integral part of the proposed contract, and the sum so certified shall not thereafter be available for expenditure for any other purpose until the obligation of the government agency concerned under the contract is fully extinguished.
SEC. 87. Void Contract and Liability of Office. — Any contract entered into contrary to the requirements of the two immediately preceding sections shall be void, and the officer or officers entering into the contract shall be liable to the government or other contracting party for any consequent damage to the same extent as if the transaction had been wholly between private parties.
The work done by [the claimant] was impliedly authorized and later expressly acknowledged by the Ministry of Public Works, which has twice recommended favorable action on the [claimant's] request for payment. Despite the admitted absence of a specific covering appropriation as required under COA Resolution 36-58, the [claimant] may nevertheless be compensated for the services rendered by it, concededly for public benefit, from the general fund allotted by law to the Betis River Project. Substantial compliance with the said resolution, in view of the circumstances of this case, should suffice. The Court also feels that the remedy suggested by [the COA], to compensation claimed, [i.e., pursuing claim before a court of law,] would entail additional expense, inconvenience and delay which in fairness should not be imposed on the [claimant.]This case was cited in Dr. Eslao v. The Commission on Audit,60 wherein we granted compensation to the contractor for some accomplished work in the project even if there was failure to go through the mandatory process of public bidding. The Court reasoned that "to deny payment to the contractor of the two buildings which are almost fully completed and presently occupied by the university would be to allow the government to unjustly enrich itself at the expense of another. Justice and equity demand compensation the basis of quantum meruit."61chanRoblesvirtualLawlibrary
Accordingly, in the interest of substantial justice and equity, the [COA] is DIRECTED to determine on a quantum meruit basis the total compensation due to the [claimant] for the services rendered by it in the channel improvement of the Betis River in Pampanga and to allow the payment thereof immediately upon completion of the said determination[.]59 (Emphasis supplied.)
COA should determine the proper amount to be paid. |
Endnotes:
1 Rollo, pp. 3-27.
2 Id. at 29-34. Composed of Chairperson Michael G. Aguinaldo, Commissioners Jose A. Fabia, and Roland C. Pondoc.
3 Id. at 29.
4 Id. at 39-40.
5 Id. at 29.
6 Id. at 41-44.
7 Id. at 29-30.
8 Id. at 29.
9 Id. at 45.
10 Id. at 46.
11 Id. at 5.
12 Id. at 47.
13 Id. at 48.
14 Id.
15 Id.
16 Id. at 49-51.
17 Id. at 52.
18 Id. at 53.
19 Id. at 56-57.
20 Id. at 58.
21 Id. at 59.
22 Id.
23 Id. at 60.
24 Id., emphasis in the original omitted.
25 Id. at 61-62.
26 Id. at 63-70.
27 Id. at 72-74.
28 Id. at 73.
29 Id. at 31.
30 Not attached in the rollo; mentioned in COA Decision dated January 10, 2020, id. at 31.
31 Id. at 31.
32 Id. at 29-34.
33 Re: Policy on the Recovery by Government Contractors on the Basis of Quantum Meruit.
34 SEC. 10. Competitive Bidding. – All Procurement shall be done through Competitive Bidding, except as provided for in Article XVI of this Act.
35 Entitled "AN ACT PROVIDING FOR THE MODERNIZATION, STANDARDIZATION AND REGULATION OF THE PROCUREMENT ACTIVITIES OF THE GOVERNMENT AND FOR OTHER PURPOSES," otherwise known as the "GOVERNMENT PROCUREMENT REFORM ACT," dated January 10, 2003.
36 SEC. 85. Appropriation before entering into contract. —
1. No contract involving the expenditure of public funds shall be entered into unless there is an appropriation therefor, the unexpended balance of which, free of other obligations, is sufficient to cover the proposed expenditure.
37 SEC. 86. Certificate showing appropriation to meet contract. — Except in the case of a contract for personal service, for supplies for current consumption or to be carried in stock not exceeding the estimated consumption for three months, or banking transactions of government-owned or controlled banks[,] no contract involving the expenditure of public funds by any government agency shall be entered into or authorized unless the proper accounting official of the agency concerned shall have certified to the officer entering into the obligation that funds have been duly appropriated for the purpose and that the amount necessary to cover the proposed contract for the current fiscal year is available for expenditure on account thereof, subject to verification by the auditor concerned. The certificate signed by the proper accounting official and the auditor who verified it, shall be attached to and become an integral part of the proposed contract, and the sum so certified shall not thereafter be available for expenditure for any other purpose until the obligation of the government agency concerned under the contract is fully extinguished.
38 Entitled "ORDAINING AND INSTITUTING A GOVERNMENT AUDITING CODE OF THE PHILIPPINES," otherwise known as the "GOVERNMENT AUDITING CODE OF THE PHILIPPINES," dated June 11, 1978.
39 SEC. 48. Void Contract and Liability of Officer. — Any contract entered into contrary to the requirements of the two (2) immediately preceding sections shall be void, and the officer or officers entering into the contract shall be liable to the Government or other contracting party for any consequent damage to the same extent as if the transaction had been wholly between private parties.
40 Executive Order No. 292, entitled "INSTITUTING THE 'ADMINISTRATIVE CODE OF 1987,'" signed on July 25, 1987.
41 Rollo, pp. 33-34.
42 Id. at 34.
43 Id. at 35-36.
44 Id. at 36.
45 Id. at 24.
46 Id. at 139-140.
47 Id. at 141-145.
48 Id. at 144.
49 Id. at 132-148.
50 See Estalilla v. Commission on Audit, G.R. No. 217448, September 10, 2019, 919 SCRA 1, 10-11.
51 Supra note 33.
52 De Guzman v. Office of the Ombudsman, 821 Phil. 681, 691 (2017).
53 RG Cabrera Corporation, Inc. v. Department of Public Works and Highways, G.R. No. 231015, January 26, 2021.
54 Supra note 37.
55 Rollo, pp. 45-60.
56 Id. at 29-36.
57 Id. at 33.
58 G.R. No. 84202, November 22, 1988, as cited in Department of Public Works and Highways v. Quiwa, 675 Phil. 9 (2011).
59 Melchor v. Commission on Audit, 277 Phil. 801, 815 (1991); and Dr. Eslao v. The Commission on Audit, 273 Phil. 97, 106-107 (1991).
60 Supra.
61 Id.
62 Supra note 59.
63 Id. at 815.
64 407 Phil. 53 (2001).
65 Id. at 62.
66 Supra note 52.
67 See Department of Public Works and Highways v. Quiwa, 681 Phil. 485, 490-492 (2012).
68 See Torreta v. Commission on Audit, G.R. No. 242925, November 10, 2020.
69 Melchor v. Commission on Audit, supra note 58.
70 Rollo, pp. 47-53.
71 Id. at 31.
72 Id. See also Certification dated January 21, 2016, id. at 60.
73 Id. at 56-57.
74 Id. at 144.cralawredlibrary